Elliston Steady & Hawes Building Ltd.
Construction of 9 Apartments at Charles Street, Ipswich, UK.
The Challenge
While constructing nine new build apartments in Charles St, Ipswich, the client found that the party walls on the project failed the pre-completion acoustic site test.
The Solution
Following consultation with JCW Acoustic Supplies, a cost effective product was identified as a quick solution. The product was JCW Silentboard
Despite high performance in reducing airborne sound transfer JCW Silentboard is of slim composition, at only 27.5mm thickness. This meant little compromise was made on the living space in the new build.
The JCW Silentboard is an ideal solution for existing walls that have failed pre-completion testing or as a solution to noisy neighbours. Once installed any decorative finish can be applied.
Results
On completion of the installation of the JCW Silentboard, on site test results showed the performance of the party walls achieving 50dB airborne sound insulation performance.
Testimonial
"JCW Silentboard was simple to install because the system was easy to work with and JCW Acoustic Supplies provided comprehensive installation guidelines. This enables our project to be completed and handed over on time."
Mick Doyle - Construction Manager.